Rebar and Structural Steel
Rebar carries the tensile forces concrete cannot. Substituting a different grade or diameter on site changes how the frame behaves in an earthquake.
Iranian reinforcing bars come in three main grades. A2, with a yield strength of 340 MPa, is semi-hard deformed bar used mostly for stirrups and transverse reinforcement. A3, at 400 MPa, is the standard longitudinal bar in beams, columns and foundations. A4, at 500 MPa, appears in special and pre-stressed structures. The difference is not only strength: ductility and bendability differ too. A4 bar is unsuitable for the tight bends of stirrups and will crack at the bend.
The weight per metre follows a simple rule: diameter squared divided by 162. A 16 mm bar therefore weighs about 1.58 kg/m. This is a practical check against underweight deliveries. If the weighbridge figure for a bundle falls more than 3 to 4 per cent below the calculated weight, the actual diameter is smaller than nominal and the steel area is less than the designer assumed. Standard bars are 12 m long and carry the mill name and grade rolled into the surface.
The most frequent execution error is swapping in a higher grade or different diameter without the structural engineer's approval. Seismic design relies on ductility, and stronger but less ductile steel can shift where the plastic hinge forms. Other recurring mistakes include shortening lap lengths, omitting spacers so the concrete cover is lost, and leaving stirrup hooks straight instead of bending them 135 degrees. All three reduce the frame's performance in an earthquake.
Light orange surface rust is harmless and even slightly improves bond, but flaking rust that peels off in layers means the section has lost material and the bar should be rejected. Do not store rebar directly on bare soil or in standing water.
Buying Tips & Quality Control
The mill name and grade are rolled into the bar; never buy unmarked rebar.
Compare weighbridge figures with calculated weight — a gap over 4 per cent means an undersized diameter.
Any change of grade or diameter must be approved in writing by the structural engineer, not decided by the steel fixer.
Ask the supplier for the standard certificate and production date
Keep Reading
Related Materials
Structural
Portland Cement and Its Types
Cement binds every concrete and mortar mix, and the correct type depends on the soil and water conditions of the site. The wrong choice quietly shortens a structure's service life.
Structural
Ready-Mix Concrete
Ready-mix is far more consistent than site-batched concrete, but final quality still rests on transport, placing and curing. The drawings set the class, not the contractor.
Structural
AAC and LECA Lightweight Blocks
Lightweight blocks cut dead load and improve the thermal performance of walls. They are non-load-bearing and must be properly tied back to the frame.